The City of Lynnwood has approximately 95 miles of roadways. Preservation of existing roads and street system has become one of the City’s priorities.
When selecting streets each year to be paved, the following criteria are considered:
The City hired a pavement management survey firm. This firm surveyed, assessed the pavement system and created a pavement management system. City of Lynnwood’s 2022 Pavement Management Analysis Report can be found here(PDF, 731KB). This process looks for cost-effective ways to balance preservation with replacement.
5 year paving program to balance preservation with replacement of the City streets.
The 2025 project activities include full depth repair and grind and overlay of pavement in selected areas.The 2025 project includes two segments: Alderwood Mall Parkway – from Alderwood Mall Boulevard to 184th St SW & 33rd Ave W – from upcoming Poplar Bridge project to 184th St SW